Grips Local 80 Building

Grips Local 80 Building

Located very close to the street created special requirements. Skin stripped from top the roofline to the base framing structure required special temporary supports during demolition.

Project Details

Project Type: Demolition
Location: Burbank, CA
General Contractor: Warner Constructors
Contact: Chris Applegate

Start Date: August 2004
Finish Date: January 2005
Contract Value: $165,000
Contract Type: Fixed Price

DSC07182_782p
previous arrow
next arrow

Job Highlights

  • Complete office renovations required both soft and hard demolition
  • Concrete sawing and cutting of exterior tilt-up walls to accommodate new entrance and windows and doors
  • Simultaneous onsite operation with other trades
  • Worked performed around live electric, plumbing, and fire sprinklers, requiring extreme sensitivity to safety issues
  • Rain near end of project created additional pumping requirements
  • Concrete canopy entryway removed adjacent street level
  • Pedestrians walkway against the site

Summary

Fast Forward was selected as the demolition contractor by Warner Constructors because they are known to specialize in difficult and unusual projects. Also, since the Grips are an entertainment industry union, they require union contractors to be hired for their projects.

The Grips office building is a 3 story, more than 20,000 square feet structure, originally built more than 20 years ago. The Grips decided to completely renovate their offices, which meant the demolition contractor selectively gut out the interior leaving a few walls in the back half of the building.

The roof remained standing and Fast Forward stripped an exterior band from the roof line (penthouse) to the base framing system. A major part of the project was to cut openings for new windows and doors in the exterior tilt up walls as the plans called for moving the entrance from the front to the side facing the parking lot. There was a concrete canopy entryway on the front which was removed. Additionally, there were sections of concrete flooring on the first and second levels that were cut and removed. Asphalt sections were cut and debris hauled away.

Fast Forward’s expertise was called into play on this job because they had to work around live electrical, plumbing and fire systems. Also, there were tight working conditions in the front since the building is located next to the sidewalk, where foot traffic was only blocked by a temporary walkway, resulting in difficulties getting equipment in and out of the area. Because heavy equipment couldn’t be raised up, the second and third floors were demolished by hand. The foundation needed shoring up during the process, so Fast Forward needed to team up with the shoring contractor to complete the task.

Burbank experienced the most rainfall in nearly 100 years near the end of this project, which set Fast Forward back nearly a week. When they could return to work they found a moat had formed around the building which had to be pumped out before any of the laborers could enter the structure.

Safety was paramount on this project since electrical, plumbing and fire systems remained live during the life of the job. The superintendent conducted weekly safety meetings, and scoured the site for potential problems everyday. When he encountered a safety issue, he called it to the attention of the crew and then addressed the best way to handle the problem immediately.

Because Fast Forward is a company who believes in excellence in the performance of their work and clean and safe conditions on their jobsites, they have successfully completed the Grips Local 80 Office Building Renovation.

Facebook Feed

Another project in progress, and we’re proud to be on site delivering precise street cutting for the Lancaster Health District Phase 2 project.A big thank you to @Toro Enterprises Inc for the continued support and ongoing opportunities to work together. We truly appreciate the trust and confidence in the Fast Forward Concrete Cutting team.Our crew is performing flat sawing and street cutting through approximately 5" thick asphalt and concrete, with a strong focus on clean, accurate, and controlled cuts.When the job requires precision street cutting, our experienced team has the equipment, expertise, and coordination to get it done right. πŸ’ͺWe look forward to keeping the work moving forward! 🀝#FastForwardConcreteCutting #ConcreteCutting #FlatSawing #StreetCutting #AsphaltCutting #PrecisionCutting #LancasterCA #LancasterHealthDistrict #Construction #ConcreteContractor #SawCutting #ConstructionInProgress #PrecisionCoordinationPerformance@metropolis disposal ... See MoreSee Less
View on Facebook
At @fastforwardconcretecutting , every new client is the beginning of a relationship we're committed to earning through quality work, reliability, and exceptional service. Many of the clients who first trusted us years ago continue to work with us today, and we're excited to welcome @delta4env as a valued new client.For this project at the Irvine Animal Care Center in Irvine, CA, our experienced wall saw operator completed precise selective wall sawing on an existing 8" CMU wall, including:βœ” (4) New door openings βœ” 8 Corner cores with no overcutsβœ” 10 LF straight vertical wall cutβœ” Safe, clean, and accurate hard demolition executionPrecision, planning, and attention to detail are critical on every project, and our team takes pride in delivering results that keep our clients' projects moving forward.Thank you to @delta4env for the opportunity. We look forward to building a long-lasting partnership. #ConcreteCutting #sawcutting #coredrilling #wallopenings #removal Metropolis Disposal ... See MoreSee Less
View on Facebook
🚧 Proud to Continue Our Partnership with @rudolphsletten 🚧At @fastforwardconcretecutting we truly value every opportunity to work with Rudolph & Sletten, one of our most important and preferred clients. Thank you for your continued trust and confidence in our team. We appreciate the opportunity to support another successful project together.πŸ“ Project: Caltech Manthiram Lab Phase 2πŸ“ Location: Pasadena, CAOur team recently completed selective demolition and surface preparation work, including:βœ”οΈ Demolition of temporary partitions while carefully protecting existing utilities running through the wallβœ”οΈ Removal of resilient flooringβœ”οΈ Epoxy floor coating removal across approximately 1,281 square feet using a planetary floor grinder to prepare the laboratory for its next phase of constructionβœ”οΈ Safe and efficient material removal and site cleanup utilizing the appropriate equipment, including a scissor lift and bobtail truckLaboratory renovations demand precision, planning, and careful execution to protect surrounding infrastructure while keeping projects moving forward. Our experienced crew takes pride in delivering safe, clean, and high-quality work on every job.Thank you again to Rudolph & Sletten for your continued partnership. We look forward to supporting many more successful projects together.Fast Forward Concrete CuttingPrecision. Coordination. Performance.#FastForwardConcreteCutting #SelectiveDemolition #ConcreteCutting #SurfacePreparation #FloorGrinding #PlanetaryGrinder #EpoxyRemoval #Construction #CommercialConstruction #LaboratoryConstruction #Caltech #Pasadena #RudolphAndSletten #SafetyFirst #Teamwork #QualityWork@pdqequipment Metropolis Disposal ... See MoreSee Less
View on Facebook

About

Fast Forward is family owned and operated concrete cutting contractor in Los Angeles, CA. Since 1990, we’ve built our reputation by providing unparalleled service, hiring only the best trained personnel in the concrete cutting business and investing in top of the line equipment. Once you hire us, you will not have to worry about anything else.

Job Opportunities

review us on google my businessread our Facebook reviewsread our Nicejob reviews