Apple Store

Apple Store

In Confined Spaces “Everything had to go just right! If anyone is late, the entire project misses the Grand Opening.”

Project Details

Project Type: Demolition
Location: Santa Monica, CA
General Contractor: DPR Construction
Contact: Doug Allen

Start Date: March 2003
Finish Date: July 2003
Contract Value: $60,000
Contract Type: Fixed Price

wwfront1_782p
previous arrow
next arrow

Job Highlights

  • Extremely tight, unchangeable deadlines
  • All work had to be performed from within the building itself
  • Only one small doorway was available to move all equipment, materials, and men through simultaneous demolition and construction
  • Job site was in the middle of a pedestrian zone
  • Unknown existing building structures
  • Pedestrians will be walking right up against the site
  • No room for heavy equipment
  • Restricted work hours

Summary

This building, built in 1955, had a long history in it’s last configuration as a clothing store. There was a large concrete foundation covering the entire first floor. In the back third, there was a second story with storage and offices. In 1955 you could use virtually any kind of building material including asbestos. The building codes were not nearly as strict as they are today. There were not even current building plans to work from. Grand opening plans were already in process, and the entire construction schedule was tight. Schedule slippage on any step, by any one of the many contractors, including Fast Forward, put the whole project in jeopardy of missing the grand opening. Because of this tight schedule, demolition and construction work began simultaneously.

The job involved several aspects of demolition. Each layer had to be peeled away to expose what was underneath. The thickness of the foundation or where pipes were located was not even known.The old floor tile covering the entire ground floor had an asbestos base. Fast Forward coordinated with the hazardous abatement subcontractor to remove the tiles. Further complicating matters, asbestos was discovered in some of the ceiling tiles, and insulation issues with the heating and air conditioning (HVAC) Insulation.

The project, located in a prime shopping and tourist area in Santa Monica, the 3rd Street Promenade, complicated the situation. Work started by erecting a protective barrier that extended out far enough to provide a safe working area in front of the building, while not interfering with the flow of foot traffic. There was no closing the street or sidewalks. Safety for both the public and the work crew was paramount. The city imposed other restrictions. Work hours were designated from 8:00 AM to 3:30 PM, equipment was not allowed in or out via the front; the alley in back was to remain accessible to surrounding businesses.

Once all the hazardous materials were removed, Fast Forward began gutting the remaining building. The façade on the front had to be removed piecemeal. After the front signs were removed, the remainder of the façade was removed, layer by layer, back to the brick structure. Several layers of various ceramic materials were encountered, each chipping apart differently.

No chances could be taken that a chip may fly out and injure someone. The entire front of the building was covered with tarps. All work was performed under the tarps in the hot sun. Jack hammers and chipping guns were used in the confined space, while working on mobile scaffolding, to chip away the facade in a carefully controlled process. Not a single piece of the façade ended up outside the protective perimeter. Supervisors were on site at all times to make sure the demolition efforts were well coordinated with construction. Even with both teams simultaneously onsite, no work site injuries occurred while Fast Forward was on the project.The interior was to be completely repartitioned, so the insides were gutted without altering or damaging the existing superstructure. In addition, the existing heating and air conditioning (HVAC) ducting and equipment was removed without damaging any of the ceiling framing. Each unit and the duct work was carefully disassembled, and one piece at a time, lowered and removed. All interior lighting, stairways and office finishing were to be removed. In addition, the lighting in the building was so old the fixtures had to be treated as hazardous waste. Fast Forward met these challenges without any site contamination.

At this point, the interior foundation was carefully sawcut from the street sidewalk leaving a clean edge to city property. The front four fifths of the foundation was removed in small sections to allow construction efforts to continue at the same time. Moving large blocks of cut concrete, and other debris posed special safety concerns. Utilizing both supervisory personnel and additional coordination personnel, Fast Forward completed the process in a timely manner, with no onsite incidents.

The city of Santa Monica’s permit process requires mandatory recycling. There were no onsite space to make scrap piles, no place to bring in large refuse hauling trucks, and only one small doorway to move men and equipment and materials through. Essentially, all equipment and supplies for both demolition and construction had to be inside the building at all times! Fast Forward overcame all of these difficulties by moving all demolition materials to a 40 yard bin tucked into the corner of the alley. The debris was then hauled to an offsite facility where the materials were sorted for recycling.

Everything on this project was controlled to the smallest detail to meet the time requirement established by the owner in order to make their grand opening date, which could not be extended. Fast Forward met all the deadlines, avoided any damage to surrounding properties, prevented onsite injuries, met all the items specified in the contract requirements, managed all of the material recycling and hazardous waste disposal.

Facebook Feed

Another project in progress, and we’re proud to be on site delivering precise street cutting for the Lancaster Health District Phase 2 project.A big thank you to @Toro Enterprises Inc for the continued support and ongoing opportunities to work together. We truly appreciate the trust and confidence in the Fast Forward Concrete Cutting team.Our crew is performing flat sawing and street cutting through approximately 5" thick asphalt and concrete, with a strong focus on clean, accurate, and controlled cuts.When the job requires precision street cutting, our experienced team has the equipment, expertise, and coordination to get it done right. 💪We look forward to keeping the work moving forward! 🤝#FastForwardConcreteCutting #ConcreteCutting #FlatSawing #StreetCutting #AsphaltCutting #PrecisionCutting #LancasterCA #LancasterHealthDistrict #Construction #ConcreteContractor #SawCutting #ConstructionInProgress #PrecisionCoordinationPerformance@metropolis disposal ... See MoreSee Less
View on Facebook
At @fastforwardconcretecutting , every new client is the beginning of a relationship we're committed to earning through quality work, reliability, and exceptional service. Many of the clients who first trusted us years ago continue to work with us today, and we're excited to welcome @delta4env as a valued new client.For this project at the Irvine Animal Care Center in Irvine, CA, our experienced wall saw operator completed precise selective wall sawing on an existing 8" CMU wall, including:✔ (4) New door openings ✔ 8 Corner cores with no overcuts✔ 10 LF straight vertical wall cut✔ Safe, clean, and accurate hard demolition executionPrecision, planning, and attention to detail are critical on every project, and our team takes pride in delivering results that keep our clients' projects moving forward.Thank you to @delta4env for the opportunity. We look forward to building a long-lasting partnership. #ConcreteCutting #sawcutting #coredrilling #wallopenings #removal Metropolis Disposal ... See MoreSee Less
View on Facebook
🚧 Proud to Continue Our Partnership with @rudolphsletten 🚧At @fastforwardconcretecutting we truly value every opportunity to work with Rudolph & Sletten, one of our most important and preferred clients. Thank you for your continued trust and confidence in our team. We appreciate the opportunity to support another successful project together.📍 Project: Caltech Manthiram Lab Phase 2📍 Location: Pasadena, CAOur team recently completed selective demolition and surface preparation work, including:✔️ Demolition of temporary partitions while carefully protecting existing utilities running through the wall✔️ Removal of resilient flooring✔️ Epoxy floor coating removal across approximately 1,281 square feet using a planetary floor grinder to prepare the laboratory for its next phase of construction✔️ Safe and efficient material removal and site cleanup utilizing the appropriate equipment, including a scissor lift and bobtail truckLaboratory renovations demand precision, planning, and careful execution to protect surrounding infrastructure while keeping projects moving forward. Our experienced crew takes pride in delivering safe, clean, and high-quality work on every job.Thank you again to Rudolph & Sletten for your continued partnership. We look forward to supporting many more successful projects together.Fast Forward Concrete CuttingPrecision. Coordination. Performance.#FastForwardConcreteCutting #SelectiveDemolition #ConcreteCutting #SurfacePreparation #FloorGrinding #PlanetaryGrinder #EpoxyRemoval #Construction #CommercialConstruction #LaboratoryConstruction #Caltech #Pasadena #RudolphAndSletten #SafetyFirst #Teamwork #QualityWork@pdqequipment Metropolis Disposal ... See MoreSee Less
View on Facebook

About

Fast Forward is family owned and operated concrete cutting contractor in Los Angeles, CA. Since 1990, we’ve built our reputation by providing unparalleled service, hiring only the best trained personnel in the concrete cutting business and investing in top of the line equipment. Once you hire us, you will not have to worry about anything else.

Job Opportunities

review us on google my businessread our Facebook reviewsread our Nicejob reviews